Concrete calculator

Cubic yards, bag counts and ready-mix cost. Add every pour on the job to one list and get a single order figure.

0.00 cubic yards
incl. waste
0.00 m³  ·  0.0 cu ft
80 lb bags
0
0.60 cu ft each
60 lb bags
0
0.45 cu ft each
40 lb bags
0
0.30 cu ft each

Your project

Every pour you add shows up here. The total is what you order.

PourDimensionsCu yd
Nothing added yet.
Project total (incl. waste)0.00 cu yd
Estimated concrete cost$0

Order the truck, not the number. A standard mixer holds about 10 cubic yards, and most suppliers charge a short-load fee under 4–5 yards. Running out mid-pour costs far more than over-ordering, which is why the waste field defaults to 10%. Confirm slump, mix design and aggregate size with your supplier — this figure is volume only.
How this is calculated

Slab, footing and wall: length × width × thickness, converted to cubic feet, divided by 27 to get cubic yards.

Round column: π × radius² × height.

Stairs: treated as a stack of rectangular slabs — the bottom step runs the full depth, each step above it one run shorter. Volume = width × run × rise × (N × (N+1) ÷ 2), where N is the number of steps. An optional landing is added on top.

Bag yields are the manufacturer standards: an 80 lb bag of mixed concrete yields about 0.60 cu ft, a 60 lb bag about 0.45, a 40 lb bag about 0.30. Bag counts are rounded up — you cannot buy three-fifths of a bag.

Waste is applied to the finished volume. 10% is a sensible default for a formed pour on flat ground; go to 15% or more for uneven subgrade, hand-dug footings, or anything you cannot screed flat.

Bags or a truck?

Rough rule: under about half a cubic yard, bags are fine. Half a yard is roughly 23 × 80 lb bags — around 1,840 lb of material to carry, mix and place before it sets. Past that, mixing by hand stops being economical and starts being a cold joint waiting to happen. Above a yard, call the supplier.

Volume estimate only. Verify against your supplier's figures and your own site measurements before ordering. Not a substitute for an engineered design.

Questions

How many cubic yards of concrete do I need for a slab?

Multiply length by width by thickness, all in feet, then divide by 27. A 20 by 12 ft slab at 4 inches thick is 20 x 12 x 0.333 = 80 cubic feet, which is 2.96 cubic yards. Add 10% for waste and you are ordering 3.26. The calculator above does this for you and handles footings, columns, walls and stairs too.

How many 80 lb bags of concrete are in a cubic yard?

Forty-five. An 80 lb bag of mixed concrete yields about 0.60 cubic feet, and there are 27 cubic feet in a yard. A 60 lb bag yields about 0.45 cubic feet, so you need 60 of those, and a 40 lb bag yields about 0.30, so you need 90.

Should I use bags or order ready-mix?

Rough rule: under about half a cubic yard, bags are fine. Half a yard is roughly 23 x 80 lb bags — around 1,840 lb of material to carry, mix and place before it starts setting. Past that, mixing by hand stops being economical and starts being a cold joint waiting to happen. Above a yard, call the supplier.

How much waste should I add to a concrete order?

10% is a sensible default for a formed pour on flat ground, which is what this calculator uses. Go to 15% or more for uneven subgrade, hand-dug footings, or anything you cannot screed flat. Running out mid-pour costs far more than over-ordering does.

How much concrete does a truck hold?

A standard mixer holds about 10 cubic yards. Most suppliers also charge a short-load fee under roughly 4 to 5 yards, so a small pour can carry a surcharge. The calculator has a short-load minimum field so you can price that in.

How do I calculate concrete for stairs?

Treat the stairs as a stack of rectangular slabs: the bottom step runs the full depth, each step above it one run shorter. Volume = width x run x rise x (N x (N+1) / 2), where N is the number of steps. The stairs tab above runs that formula and lets you add a landing on top.