Enter your areas; the sheet turns them into cubic yards, sod pallets and a priced estimate you can hand to the customer.

Download the template

Excel file. No email, no signup. Yours to edit.

3 tabs · 102 formulas · Works in Excel, Google Sheets and LibreOffice

TabWhat it does
Read MeHow the sheet works, which cells to change, and which to leave alone.
TakeoffOne row per area or bed. Enter length, width, a sod flag and a depth in inches. It returns square feet, cubic yards to order and sod pallets.
EstimateMaterials, labour, overhead, profit and tax, with a price per square foot of treated area at the bottom.

How the takeoff works

Each row on the Takeoff tab is one area or bed. Enter length and width. If it gets sod, put a 1 in the Sod? column. If it gets bulk material — mulch, topsoil, crushed stone — enter the depth in inches.

The sheet does the rest. Area in square feet. Raw cubic yards: area × depth ÷ 12 ÷ 27. Then cubic yards to order, with a 10% over-order built in. You can change that percentage, but order a little over. A short load on a 40-minute drive costs you more than the extra yard did.

Suppliers sell stone by the ton and mulch by the yard, so the sheet gives you both. Crushed stone runs about 1.4 tons per cubic yard; sand and topsoil run lighter.

The costs that sink landscaping bids

Material take-offs are the easy part. The jobs that lose money lose it on access and disposal, so the Estimate tab has lines for both.

  • Access. A backyard you can only reach through a 36-inch gate turns a wheelbarrow job into a day rate. No skid steer, no dump trailer backed up to the bed. Price it with the difficult-access surcharge, not out of your profit.
  • Disposal. Hauling away old sod costs you at both ends: labour to cut and load it, then a tip fee to drop it. There are separate lines for removal and for disposal because they are separate costs.
  • Watering-in. If you guarantee the sod takes, you own the watering. The sheet has a line for watering-in and first cut. Price it or put the watering schedule in writing as the customer's job.

And before any of it: call before you dig. Locating buried utilities is a legal requirement in most jurisdictions, and the locate is free. In the US, dial 811.

Overhead, profit and what you actually make

The Estimate tab adds 10% overhead to your costs, then 10% profit on top of that, then tax. Both percentages are editable, and you should know what they actually give you: 10% then 10% is a 1.21 multiplier, which works out to a 17.4% gross margin — not 20%. If you want a true 20%, raise the numbers.

The sheet also reports price per square foot of treated area. Track it across a few jobs and you will start quoting small work over the phone with some confidence — and spotting the bids where you have forgotten something, because the number comes out too low.

Check the defaults against your supplier. The sheet assumes 450 sq ft of coverage per sod pallet, 1.4 tons per cubic yard for crushed stone (sand and topsoil run about 1.2 to 1.35), and a 10% over-order. Pallet sizes vary by grower and weights vary by material, so all of these are editable cells. Set them once to match who you buy from and leave them.

Questions

How many cubic yards of mulch do I need?

Multiply the area in square feet by the depth in inches, divide by 12, then divide by 27. A 500 sq ft bed at 3 inches deep is 500 × 3 ÷ 12 ÷ 27, about 4.6 cubic yards — order 5. The Takeoff tab runs this formula for every row and adds a 10% over-order so you are not making a second trip for one yard.

How much sod does a pallet cover?

It varies by grower — most pallets cover somewhere around 400 to 500 sq ft. The template defaults to 450 sq ft per pallet and rounds up, since you cannot buy part of a pallet. A 1,000 sq ft front lawn comes to 3 pallets, which is $555 at $185 a pallet. The coverage figure is an editable cell, so set it to whatever your supplier actually ships.

How many tons is a cubic yard of gravel?

Crushed stone runs about 1.4 tons per cubic yard. Sand and topsoil are lighter, roughly 1.2 to 1.35. The sheet shows both yards and tons because suppliers quote stone by the ton but mulch by the yard, and you need the right unit for each phone call.

I set 10% overhead and 10% profit. Why is my margin not 20%?

Because the percentages stack as markup, not margin. Cost × 1.10 × 1.10 is a 1.21 multiplier, and 0.21 of 1.21 is a 17.4% gross margin. That is how most estimating sheets work, this one included. If your business needs a true 20% margin, raise the profit percentage until the bottom line gets there.

Is the template actually free?

Yes. It is a plain .xlsx file with 102 working formulas — a real calculating spreadsheet, not a PDF of a blank form. No macros, so it opens cleanly in Excel, Google Sheets and LibreOffice. Download it, put your own prices in, and it is yours.